Project Brief

The restoration of windows at Stocks Court which is part of the Mile End QMUL Campus was a project that required speed and quality to ensure that the scaffolding could be efficiently erected and struck in time for the new student term.


Scope of Works

Painting & Decorating works started on the 21st of July 2019 and comprised of external decoration to the following:

· Strip back and redecorate 150 windows and entrance doors

· Strip back and decorate all metal railings and ironmongery


Key Challenges

With the project being based in such proximity to the public, it was of utmost importance that the public were kept safe from the working area, this was achieved by erecting chapter 8 barriers and a significant signage, ensuring that walkways were kept safe and maintained at all times.


Overall Output

· Delivery of project on time for new term

· Preserving the windows for the foreseeable future

· Completed works with minimal disruption to tenants and the public