Project Brief

Pembroke & Bull were appointed to undertake decoration works to 74 apartments over 13 floors including common parts, main entrance and back of house areas.

The site occupies a pivotal location within both the Regent’s Canal and King’s Cross Conservation Areas and forms part of a ‘gateway’ to the future Camley Street regeneration area.


Scope of Works

Painting & Decorating works started on the 21st of July 2021 and consisted of decorations to the following:

· Apartments from Lower Ground to the 11th Floor

· Spraying to Soffits and Services including Ductwork, Vents, AC Units and Cable Trays

· Decorations to the Reception, Main entrance Space, Post Room and Back of House Areas

Key Challenges

With new tenants poised to move in, it was paramount that all apartments were decorated on time, ready for the new occupants.

The team worked closely with the main contractor moving from top to bottom allowing finishing trades to follow installing carpets and undertake a builders clean.


Overall Output

The project was completed as per programme with tenants moving in on time.

Following on from a successful handover of the north and south towers the buildings are now in occupancy of the client ready for the new tenants.