Queen Mary University – Student Accommodation

Value: £800,000

Location: E1 and EC1M – London

Duration: 12 weeks

Project Brief

Pembroke & Bull Contracts Ltd was appointed to undertake decoration works to approximately 750 student accommodation rooms across nine buildings within Queen Mary University’s Mile End and Barbican campuses. The programme required coordinated delivery across multiple sites within a fixed academic timeframe.

Scope of Works

Decoration to bedrooms and associated common parts across the following buildings:

  • Maynard House – 100 rooms
  • Varey House – 100 rooms
  • Pooley House –378 rooms
  • Chapman House –31 rooms
  • Chesney House – 31 rooms
  • Selincourt House – 31 rooms
  • Dawsons Hall – 203 rooms total
  • Lodge House – 18 rooms
  • Lindop House – 120 rooms

Challenges & Solutions

Works were delivered during the COVID-19 pandemic, requiring careful workforce segregation and management. Operatives were split across separate floors to maintain social distancing, allowing any affected areas to be isolated if required. The programme allowed no extension due to student occupation dates.

Results

Through effective sequencing and labour management, the programme was accelerated by two weeks. The project was completed with no issues raised by the client or campus staff, with both the university and the main contractor expressing satisfaction with the scale, organisation, and quality of the works delivered.